Latest News | March 25th, 2021

Update 25th March 2021

Works are progressing and we really feel like we are going up in the world.  The second floor slab was poured on Tuesday and we can now clearly see the sea in the distance from the terraces of what will be bedrooms in the Amelia and Mariana houses.  Work progresses with pouring the columns and ring beams to support the roof structure and we expect to pour the roof concrete just after Easter.  Meanwhile, in the garage, although we have hit a considerable amount of rock, work is progressing and the retaining walls for the garage are being poured one by one.  Soon the walls will be complete and then the floor and roof slabs will quickly follow, giving us a great idea of how the garden is going to take shape.