Its been a few weeks since the last update and lots has been happening. The structure of building has been completed including the roof and works has now started on laying out the Casas in blockwork. The base works of the drainage services have been installed and final decisions have been made on kitchen and bathroom layouts (always minor adjustments when you see where things physically go) as well as final decisions on doors, glazing, ironmongery, tiling and flooring.
In the garage, the drainage works have to be finalised before the floor slab can be finally poured although the roof slab including the swimming pool have been cast.
In the coming week, the insulation and plastering works will start and the stairs in the Casa 1 (Amelia) will be finished. Very shortly, the underfloor heating circuits will be laid out The subcontractors are preparing the list of finishes and locations of lighting, sockets and sanitary ware and ventilation /airconditioning.
If you would like to buy one of these homes,
please contact the sales agent:
MAP – Martina Lennon Properties
Or enter your contact details below:
A development by Fascínio Vintage. Website by apricot.ie